- What is the Schedule Performance Index (SPI) calculated using Earned Value Management?
- EV / AC (Earned Value divided by Actual Cost)
- EV / PV (Earned Value divided by Planned Value)
- PV / AC (Planned Value divided by Actual Cost)
- AC / EV (Actual Cost divided by Earned Value)
- Which of the following is a tool used to graphically display the logical relationships and the sequence in which project activities must be completed?
- Work Breakdown Structure (WBS)
- Responsibility Assignment Matrix (RAM)
- Project Schedule Network Diagram
- Resource Breakdown Structure (RBS)
- A project manager is asked to shorten the project schedule by four weeks. The critical path has three activities with durations of 8, 10, and 6 weeks respectively. Which schedule compression technique would be MOST appropriate to consider FIRST?
- Reducing the project scope.
- Fast tracking the activities.
- Crashing the activities on the critical path.
- Negotiating a later delivery date.
- Which of the following is a key input to the Sequence Activities process?
- Activity Attributes
- Project Budget
- Risk Register
- Stakeholder Management Plan
- What is the purpose of a Resource Calendar?
- To define the roles and responsibilities of project team members.
- To document the availability of project resources over time.
- To outline the communication requirements for project stakeholders.
- To track the actual utilization of project resources.
- Which of the following estimating techniques involves creating detailed estimates for each work package and then aggregating them for higher levels?
- Analogous Estimating
- Parametric Estimating
- Bottom-Up Estimating
- Three-Point Estimating
- What does a lead time in a schedule network diagram represent?
- The duration of the predecessor activity.
- The duration of the successor activity.
- The amount of time a successor activity can be started before its predecessor activity is completed.
- The amount of time a successor activity must be delayed after its predecessor activity is completed.
- During the Develop Schedule process, which of the following constraints might influence the project schedule?
- Scope creep
- Resource availability
- Stakeholder expectations
- Quality standards
- Which of the following is a primary goal of the Control Schedule process?
- To define the project activities.
- To establish the sequence of activities.
- To monitor the status of the project schedule and manage changes to the schedule baseline.
- To estimate the resources required for project activities.
- Which of the following is NOT typically included in the Activity Attributes?
- Activity ID
- Activity Name
- Resource Requirements
- Budget Estimates
- What is the primary purpose of Resource Leveling?
- To shorten the project schedule.
- To allocate the most skilled resources to critical activities.
- To adjust start and finish dates based on resource constraints.
- To reduce the overall cost of the project.
- A project has a planned duration of 12 months. After 6 months, the Schedule Performance Index (SPI) is 0.8. What does this indicate about the project schedule?
- The project is ahead of schedule.
- The project is behind schedule.
- The project is on schedule.
- It is not possible to determine the schedule status with the given information.
- Which of the following BEST describes an External Dependency?
- A dependency between project activities that are performed by the project team.
- A dependency involving activities outside of the project but necessary for project completion.
- A dependency based on the project team’s preferred sequence of activities.
- A dependency that is legally or contractually required.
- What is the significance of the Critical Chain Method in project scheduling?
- It focuses on managing the critical path and resource constraints.
- It prioritizes activities based on their cost.
- It emphasizes stakeholder involvement in schedule development.
- It uses probabilistic methods to estimate activity durations.
- Which of the following is a key output of the Control Schedule process?
- Project Schedule
- Activity List
- Schedule Forecasts
- Resource Calendars
- Which estimating technique is often used when there is limited information about the project?
- Bottom-Up Estimating
- Parametric Estimating
- Analogous Estimating
- Three-Point Estimating
- What is a hammock activity in project scheduling?
- A summary activity that spans between two milestones or activities.
- An activity with zero duration.
- An activity that can be performed in parallel with other activities.
- An activity that is not on the critical path.
- During schedule development, which of the following should be considered when determining activity dependencies?
- Resource availability
- Project budget
- Scope statement
- Risk management plan
- Which of the following is the MOST appropriate action when a significant schedule delay is unavoidable?
- Ignore the delay and hope the subsequent activities can catch up.
- Immediately reduce the project scope to meet the original deadline.
- Communicate the potential impact of the delay to the stakeholders and explore options.
- Reassign resources from non-critical activities to the delayed activity.
- Which of the following is a key element of the Schedule Baseline?
- Activity list and duration estimates.
- Approved start and finish dates for schedule activities.
- Resource allocation and cost estimates.
- Risk register and mitigation plans.
- What is the purpose of a Monte Carlo simulation in project schedule management?
- To identify the critical path with certainty.
- To determine the exact finish date of the project.
- To analyze the probability of meeting different schedule targets.
- To optimize resource allocation across project activities.
- Which of the following is a tool or technique used in the Sequence Activities process?
- Precedence Diagramming Method (PDM)
- Critical Path Method (CPM)
- Earned Value Management (EVM)
- Resource Leveling
- What is the difference between a lag and a lead in schedule network diagrams?
- Lag indicates acceleration, while lead indicates a delay.
- Lag indicates a delay, while lead indicates acceleration.
- Lag applies only to Finish-to-Start dependencies, while lead applies to Start-to-Start dependencies.
- Lag reduces activity duration, while lead increases activity duration.
- During project monitoring and controlling, if the Schedule Variance (SV) is negative, it indicates that:
- The project is ahead of schedule.
- The project is behind schedule.
- The project is under budget.
- The project is over budget.
- Which of the following is NOT a typical output of the Develop Schedule process?
- Project Schedule
- Schedule Baseline
- Resource Calendars
- Stakeholder Register
- Which estimating technique is generally the MOST accurate but also the most time-consuming?
- Analogous Estimating
- Parametric Estimating
- Bottom-Up Estimating
- Three-Point Estimating
- What is the purpose of a milestone chart?
- To show the detailed sequence of project activities.
- To track the resource utilization over the project lifecycle.
- To present a summary-level view of key project milestones and their planned completion dates.
- To analyze the cost performance of the project against the budget.
- When defining activities, what level of decomposition is generally recommended?
- Decompose activities until they are the responsibility of a single individual.
- Decompose activities to the lowest possible level to ensure maximum control.
- Decompose activities into work packages that can be realistically estimated and managed.
- Decompose activities based on the phases of the project lifecycle.
- Which of the following is a proactive way to deal with potential schedule risks?
- Ignoring the risks until they materialize.
- Developing contingency plans and schedule reserves.
- Immediately crashing the schedule when a risk occurs.
- Reducing the project scope to avoid potential delays.
- Which of the following is a key benefit of having a well-defined Schedule Management Plan?
- It ensures that all stakeholders have the same understanding of how the schedule will be managed.
- It guarantees that the project will be completed on time.
- It eliminates the need for schedule monitoring and control.
- It simplifies the process of resource allocation.
- What is the formula for calculating the Estimate to Complete (ETC) when the current variances are considered atypical and future performance is expected to be based on the original plan?
- ETC = EAC – AC
- ETC = BAC – EV
- ETC = (BAC – EV) / CPI
- ETC = (BAC – EV) / SPI
- Which of the following is a method used to visually represent the project schedule and monitor its progress against the baseline?
- Pareto Chart
- Fishbone Diagram
- Tracking Gantt Chart
- Scatter Diagram
- A project team is consistently missing its activity deadlines. As a project manager, what should be your FIRST step in addressing this issue?
- Reprimand the team members for poor performance.
- Immediately revise the project schedule.
- Analyze the reasons for the delays.
- Reallocate resources to expedite the remaining activities.
- Which of the following is a key consideration when establishing dependencies between project activities?
- The skills of the assigned resources.
- The cost of performing the activities.
- The logical relationships and constraints.
- The communication preferences of the stakeholders.
- What is the purpose of a Time Buffer in the Critical Chain Method?
- To protect individual tasks from delays.
- To aggregate buffers at the end of the critical chain and feeding chains.
- To ensure that resources are always fully utilized.
- To protect the critical chain from delays in non-critical path activities.
- Which of the following is a potential drawback of using Crashing to shorten the schedule?
- Reduced project quality.
- Decreased team morale.
- Increased project cost.
- All of the above.
- What is the primary focus of the Plan Schedule Management process?
- Defining the activities and their durations.
- Establishing the policies and procedures for managing the project schedule.
- Creating the project schedule baseline.
- Monitoring and controlling the project schedule.
- Which of the following is a key input to the Estimate Activity Resources process that is also an output of the Define Activities process?
- Activity List
- Resource Calendar
- Project Charter
- Enterprise Environmental Factors
- What is the impact of a positive float on a project activity?
- It means the activity is on the critical path.
- It indicates the activity can be delayed without affecting the project finish date.
- It suggests the activity is taking longer than planned.
- It requires immediate corrective action.
- Which of the following is a characteristic of Parametric Estimating?
- It uses expert judgment and historical data from similar projects.
- It relies on statistical relationships between variables.
- It involves a detailed breakdown of work packages.
- It provides a range of possible durations based on optimistic, pessimistic, and most likely estimates.
- What is the formula for calculating the To-Complete Performance Index (TCPI) based on the Budget at Completion (BAC)?
- TCPI = EV / AC
- TCPI = (BAC – EV) / (BAC – AC)
- TCPI = (BAC – EV) / (EAC – AC)
- TCPI = BAC / EAC
- Which of the following is a benefit of using a Project Management Information System (PMIS) for schedule management?
- It eliminates the need for a project manager.
- It automatically resolves resource conflicts.
- It facilitates the creation, maintenance, and communication of the project schedule.
- It guarantees that the project will be delivered within the original timeframe.
- A project stakeholder requests a change that will likely impact the project schedule. What should the project manager do FIRST?
- Immediately implement the change.
- Reject the change request to avoid schedule delays.
- Assess the potential impact of the change on the schedule.
- Update the project schedule to reflect the requested change.
- Which of the following is a key element to consider when developing a realistic project schedule?
- The desired finish date communicated by the sponsor.
- The availability and capability of the project team.
- The total budget allocated for the project.
- The risk management plan and contingency reserves.
- In the Critical Chain Method, what are feeding buffers used for?
- To protect the critical chain from delays in non-critical path activities.
- To provide extra time for resource leveling.
- To account for unexpected scope changes.
- To ensure that project milestones are met on time.
- Which of the following is a potential consequence of poorly managing the project schedule?
- Increased stakeholder satisfaction.
- Improved team collaboration.
- Missed deadlines and increased costs.
- Enhanced project quality.
- What is the primary purpose of the Monitor and Control Project Work process in relation to the project schedule?
- To define the work packages and activities.
- To create the initial project schedule.
- To track project progress and manage changes to the performance baselines, including the schedule.
- To secure the necessary resources for the project activities.
- Which of the following is a key input to the Control Schedule process that provides the planned dates for activities?
- Project Charter
- Risk Register
- Schedule Baseline
- Lessons Learned Register
- What is the relationship between the Work Breakdown Structure (WBS) and the project schedule?
- The WBS defines the work to be done, and the schedule defines when the work will be done.
- The schedule is created before the WBS to define the project timeline.
- The WBS is a graphical representation of the project schedule.
- There is no direct relationship between the WBS and the project schedule.
- Which of the following is a key skill for a project manager in effectively managing the project schedule?
- Financial accounting
- Contract negotiation
- Time management and organizational skills
- Technical expertise in the project domain
Answers
- EV / PV (Earned Value divided by Planned Value)
- Project Schedule Network Diagram
- Crashing the activities on the critical path.
- Activity Attributes
- To document the availability of project resources over time.
- Bottom-Up Estimating
- The amount of time a successor activity can be started before its predecessor activity is completed.
- Resource availability
- To monitor the status of the project schedule and manage changes to the schedule baseline.
- Budget Estimates
- To adjust start and finish dates based on resource constraints.
- The project is behind schedule.
- A dependency involving activities outside of the project but necessary for project completion.
- It focuses on managing the critical path and resource constraints.
- Schedule Forecasts
- Analogous Estimating
- A summary activity that spans between two milestones or activities.
- Scope statement
- Communicate the potential impact of the delay to the stakeholders and explore options.
- Approved start and finish dates for schedule activities.
- To analyze the probability of meeting different schedule targets.
- Precedence Diagramming Method (PDM)
- Lag indicates a delay, while lead indicates acceleration.
- The project is behind schedule.
- Stakeholder Register
- Bottom-Up Estimating
- To present a summary-level view of key project milestones and their planned completion dates.
- Decompose activities into work packages that can be realistically estimated and managed.
- Developing contingency plans and schedule reserves.
- It ensures that all stakeholders have the same understanding of how the schedule will be managed.
- ETC = BAC – EV
- Tracking Gantt Chart
- Analyze the reasons for the delays.
- The logical relationships and constraints.
- To protect the critical chain from delays in non-critical path activities.
- All of the above.
- Establishing the policies and procedures for managing the project schedule.
- Activity List
- It indicates the activity can be delayed without affecting the project finish date.
- It relies on statistical relationships between variables.
- TCPI = (BAC – EV) / (BAC – AC)
- It facilitates the creation, maintenance, and communication of the project schedule.
- Assess the potential impact of the change on the schedule.
- The availability and capability of the project team.
- To protect the critical chain from delays in non-critical path activities.
- Missed deadlines and increased costs.
- To track project progress and manage changes to the performance baselines, including the schedule.
- Schedule Baseline
- The WBS defines the work to be done, and the schedule defines when the work will be done.
- Time management and organizational skills