- Which of the following BEST describes the purpose of identifying risks in a project?
- To eliminate all potential threats to the project.
- To assign responsibility for each potential risk.
- To understand potential events that could impact the project positively or negatively.
- To create a detailed plan for every possible project scenario.
- A project manager is facilitating a risk identification meeting with the project team and key stakeholders. Which of the following techniques is MOST effective for generating a comprehensive list of potential risks?
- Brainstorming
- Monte Carlo analysis
- Sensitivity analysis
- Earned Value Management
- During the risk assessment process, a risk is determined to have a high probability of occurrence and a high impact on project objectives. According to a typical probability and impact matrix, how should this risk be categorized?
- Low priority
- Medium priority
- High priority
- Monitor only
- Which of the following is an example of a positive risk (opportunity) that could be identified in a project?
- A key team member unexpectedly resigns.
- A critical supplier goes out of business.
- A new technology emerges that could significantly reduce development time.
- Changes in government regulations require additional compliance measures.
- A project team has identified several potential risks and is now determining the likelihood of these risks occurring and their potential impact on the project. Which process are they currently performing?
- Identify Risks
- Plan Risk Management
- Perform Qualitative Risk Analysis
- Perform Quantitative Risk Analysis
- Which of the following outputs of the Identify Risks process provides a structured list of identified risks along with their descriptions?
- Risk Management Plan
- Risk Register
- Risk Report
- Issue Log
- A project manager is reviewing potential risks and wants to visually represent the hierarchy of identified risks. Which of the following tools would be MOST suitable for this purpose?
- Probability and impact matrix
- Risk breakdown structure (RBS)
- Influence diagram
- Tornado diagram
- Which of the following risk response strategies aims to increase the probability and/or positive impact of an opportunity?
- Avoid
- Mitigate
- Enhance
- Accept
- A project team decides to purchase insurance to cover potential financial losses due to a specific risk. Which risk response strategy are they employing?
- Transfer
- Escalate
- Avoid
- Accept
- During a project execution, a previously unidentified risk emerges. What is the FIRST thing the project manager should do?
- Update the risk register.
- Implement the contingency plan.
- Assess the impact and probability of the new risk.
- Inform the project sponsor immediately.
- Which of the following is a key input to the Plan Risk Management process?
- Risk Register
- Project Management Plan
- Risk Report
- Lessons Learned Register
- The risk management plan should include all of the following EXCEPT:
- Roles and responsibilities for risk management activities.
- Budget and schedule for risk management activities.
- A list of all identified risks.
- Risk categories.
- Which of the following techniques uses expected monetary value (EMV) to analyze potential outcomes of different project scenarios?
- Sensitivity analysis
- Monte Carlo analysis
- Decision tree analysis
- Probability and impact matrix
- A project has a 60% chance of a $100,000 profit and a 40% chance of a $50,000 loss. What is the expected monetary value (EMV) of this project?
- $40,000
- $80,000
- $10,000
- $20,000
- Which of the following risk response strategies involves changing the project plan to eliminate the risk or protect the project objectives from its impact?
- Mitigate
- Transfer
- Avoid
- Accept
- A project manager is monitoring the risk register and notices that the probability of a specific risk has increased significantly. What should the project manager do NEXT?
- Ignore the change if the impact remains low.
- Update the project management plan.
- Re-assess the risk and its potential impact.
- Immediately implement the contingency plan.
- Which of the following is a tool and technique used in the Monitor Risks process?
- Risk breakdown structure
- Probability and impact matrix
- Risk audit
- SWOT analysis
- The process of developing options and actions to enhance opportunities and reduce threats to the achievement of project objectives is known as:
- Identify Risks
- Perform Risk Analysis
- Plan Risk Responses
- Monitor Risks
- Which of the following is NOT a typical output of the Plan Risk Responses process?
- Contingency plans
- Fallback plans
- Risk triggers
- Risk register
- A risk trigger is BEST described as:
- A potential event that could impact the project.
- A symptom or warning sign that a risk is about to occur or has occurred.
- The person responsible for managing a specific risk.
- The financial reserve allocated to address potential risks.
- Which of the following stakeholders is typically MOST involved in the risk management process?
- Project Team
- Project Sponsor
- Functional Managers
- Customers
- What is the primary purpose of a risk audit?
- To identify new risks that were not previously identified.
- To assess the effectiveness of the risk management processes.
- To determine the financial impact of realized risks.
- To assign responsibility for managing identified risks.
- Which of the following is a quantitative risk analysis technique that models a range of potential outcomes by performing multiple simulations?
- Sensitivity analysis
- Expected monetary value analysis
- Monte Carlo analysis
- Decision tree analysis
- A project manager is concerned about the impact of a delay in a critical deliverable. Which risk analysis technique would be MOST helpful in determining the potential impact of this delay on the overall project schedule?
- Probability and impact matrix
- Sensitivity analysis
- Risk register
- SWOT analysis
- Which of the following risk response strategies is appropriate for risks with a low probability and low impact?
- Avoid
- Mitigate
- Transfer
- Accept
- During project closure, what should be done with the risk register?
- Discard it as the project is complete.
- Archive it as part of the project documents for future reference.
- Update it with lessons learned about risk management.
- Use it as a template for future projects.
- Which of the following is a common cause of project risks?
- Effective communication
- Clear project objectives
- Changes in requirements
- Adequate resource allocation
- A project team is brainstorming potential risks. Which of the following is a key principle for effective brainstorming?
- Criticize ideas to ensure only the best are captured.
- Encourage everyone to contribute, no matter how unusual the idea seems.
- Focus on analyzing each risk as it is identified.
- Limit the session to a small group of experts.
- Which of the following BEST describes a contingency reserve?
- Funds allocated to address risks that are known and included in the risk register.
- Funds allocated to address unforeseen risks that were not identified during planning.
- Time added to the project schedule to account for potential delays.
- Resources allocated to implement risk response plans.
- A project manager is reviewing the risk register and notices a risk with a high impact but a very low probability. What is the MOST appropriate course of action?
- Ignore the risk due to its low probability.
- Develop a full mitigation plan.
- Monitor the risk and develop a contingency plan if necessary.
- Transfer the risk to a third party.
- Which of the following is a key benefit of performing risk management throughout the project lifecycle?
- It guarantees project success.
- It eliminates all uncertainty.
- It increases the likelihood of meeting project objectives.
- It reduces the need for project management processes.
- Which of the following is NOT a typical element of a risk management plan?
- Methodology
- Roles and responsibilities
- Risk thresholds
- Project budget
- A project team is using a probability and impact matrix. A risk with a probability of 0.8 and an impact score of 0.7 would typically fall into which category if the threshold for high risk is 0.56 (probability * impact)?
- Low
- Medium
- High
- Monitor
- Which of the following is an example of a risk trigger?
- A delay in the delivery of a key component exceeding one week.
- The project manager holding a team meeting.
- The project sponsor approving a change request.
- The completion of a major project milestone.
- What is the purpose of the Monitor Risks process?
- To identify new risks.
- To analyze the probability and impact of risks.
- To track identified risks, monitor residual risks, and identify new risks.
- To develop risk response plans.
- Which of the following is a tool used in Perform Qualitative Risk Analysis?
- Decision tree analysis
- Monte Carlo simulation
- Probability and impact matrix
- Earned Value Analysis
- A project manager is facilitating a lessons learned session at the end of a project. What information related to risk management should be captured?
- The total number of risks identified.
- The names of the individuals responsible for each risk.
- The effectiveness of the risk management processes and the outcomes of implemented risk responses.
- The initial probability and impact scores of all identified risks.
- Which of the following risk response strategies involves sharing the burden of the risk with a third party?
- Mitigate
- Transfer
- Enhance
- Accept
- A project team has identified a risk that, if it occurs, will have a significant negative impact on the project schedule but a minimal impact on the budget. Which risk response strategy might be MOST appropriate?
- Avoid
- Mitigate the schedule impact
- Transfer the budget impact
- Accept the risk
- Which of the following is a key output of the Perform Quantitative Risk Analysis process?
- Risk register updates
- Probability and impact matrix
- Risk report
- Prioritized list of quantitative risks
- Which of the following BEST describes residual risks?
- Risks that remain after risk responses have been implemented.
- Newly identified risks that emerge during project execution.
- Risks that were initially identified but later deemed insignificant.
- The potential negative consequences of implementing risk response plans.
- What is the primary goal of risk management planning?
- To identify all possible risks.
- To define how risk management activities will be conducted.
- To eliminate all risks from the project.
- To assign responsibility for all identified risks.
- Which of the following is a common input to the Perform Qualitative Risk Analysis process?
- Risk management plan
- Project budget
- Project schedule
- Stakeholder register
- A project manager is using a decision tree to analyze different project paths based on potential risks and their associated outcomes. What is the primary benefit of using this technique?
- It provides a visual representation of the risk breakdown structure.
- It helps in calculating the expected monetary value of different decisions.
- It prioritizes risks based on their probability and impact.
- It simulates a large number of possible project outcomes.
- Which of the following is NOT a typical element of the risk register?
- Identification number for each risk
- Description of the risk
- Probability and impact of the risk
- Detailed work breakdown structure (WBS)
- Which of the following risk response strategies is most suitable for opportunities with a high probability and high positive impact?
- Accept
- Enhance
- Share
- Exploit
- A project manager is reviewing the project budget and notices a significant amount allocated as management reserve. What is the purpose of the management reserve?
- To cover costs associated with implementing planned risk responses.
- To cover costs associated with unforeseen risks that were not identified during planning.
- To cover scope changes that are approved during the project.
- To cover cost overruns due to poor project performance.
- Which of the following is a key characteristic of effective risk management?
- Reactive
- Isolated
- Proactive
- Optional
- During a project meeting, a stakeholder raises a new potential risk. What should the project manager do FIRST?
- Immediately update the risk register.
- Dismiss the risk if it was not identified earlier.
- Assess the potential impact and probability of the new risk.
- Assign responsibility for the risk to a team member.
- Which of the following is a benefit of using standardized risk categories in a project?
- It ensures that all possible risks are identified.
- It provides a structured approach to risk identification.
- It eliminates the need for further risk analysis.
- It automatically assigns risk owners.
Answers
- To understand potential events that could impact the project positively or negatively.
- Brainstorming
- High priority
- A new technology emerges that could significantly reduce development time.
- Perform Qualitative Risk Analysis
- Risk Register
- Risk breakdown structure (RBS)
- Enhance
- Transfer
- Assess the impact and probability of the new risk.
- Project Management Plan
- A list of all identified risks.
- Decision tree analysis
- $40,000
- Avoid
- Re-assess the risk and its potential impact.
- Risk audit
- Plan Risk Responses
- Risk register
- A symptom or warning sign that a risk is about to occur or has occurred.
- Project Team
- To assess the effectiveness of the risk management processes.
- Monte Carlo analysis
- Sensitivity analysis
- Accept
- Archive it as part of the project documents for future reference.
- Changes in requirements
- Encourage everyone to contribute, no matter how unusual the idea seems.
- Funds allocated to address unforeseen risks that were not identified during planning.
- Monitor the risk and develop a contingency plan if necessary.
- It increases the likelihood of meeting project objectives.
- Project budget
- High
- A delay in the delivery of a key component exceeding one week.
- To track identified risks, monitor residual risks, and identify new risks.
- Probability and impact matrix
- The effectiveness of the risk management processes and the outcomes of implemented risk responses.
- Transfer
- Mitigate the schedule impact
- Prioritized list of quantitative risks
- Risks that remain after risk responses have been implemented.
- To define how risk management activities will be conducted.
- Risk management plan
- It helps in calculating the expected monetary value of different decisions.
- Detailed work breakdown structure (WBS)
- Exploit
- To cover costs associated with unforeseen risks that were not identified during planning.
- Proactive
- Assess the potential impact and probability of the new risk.
- It provides a structured approach to risk identification.