- Which of the following BEST describes the primary purpose of conducting a procurement audit?
- To ensure the seller is adhering to the contract terms.
- To identify lessons learned in the procurement process.
- To verify that the buyer’s procurement policies were followed.
- To assess the financial health of the seller.
- A project team needs to acquire a complex software system. Due to the specialized nature of the product, there are only a few potential sellers. Which contract type would MOST likely be used in this situation?
- Firm-Fixed-Price (FFP)
- Cost-Plus-Fixed-Fee (CPFF)
- Time and Materials (T&M)
- Purchase Order
- During the Plan Procurement Management process, which document outlines the specific products, services, or results to be acquired from outside the project team?
- Procurement Management Plan
- Statement of Work (SOW)
- Source Selection Criteria
- Make-or-Buy Analysis
- Which of the following is NOT a tool or technique used in the Conduct Procurements process?
- Bidder conferences
- Proposal evaluation
- Independent cost estimates
- Negotiations
- A project manager is managing a contract where the seller is consistently late in delivering key components. What should the project manager do FIRST?
- Immediately terminate the contract due to breach of agreement.
- Issue a formal warning letter to the seller outlining the consequences of further delays.
- Review the contract terms and conditions regarding delays and potential remedies.
- Withhold payment until the outstanding components are delivered.
- What is the PRIMARY output of the Control Procurements process?
- Closed procurements
- Seller invoices paid
- Approved change requests
- Procurement performance reports
- Which of the following describes a unilateral contract?
- An agreement where both parties make promises.
- An agreement where one party makes an offer that can only be accepted by the other party’s performance.
- A contract with clearly defined terms and conditions.
- A contract that is implied rather than explicitly stated.
- During the source selection process, what is the purpose of using weighting systems for evaluation criteria?
- To ensure all proposals are evaluated equally.
- To emphasize the importance of certain criteria over others.
- To simplify the comparison of complex proposals.
- To comply with organizational procurement policies.
- A buyer is using a Cost-Plus-Incentive-Fee (CPIF) contract. The target cost is $100,000, the target fee is $10,000, and the sharing ratio is 80/20 (buyer/seller). If the actual cost is $90,000, what is the total amount the seller will be paid?
- $98,000
- $112,000
- $110,000
- $108,000
- What is the BEST time to involve legal counsel in the procurement process?
- Only when disputes arise with sellers.
- After the contract has been drafted by the project team.
- Early in the Plan Procurement Management process.
- Just before the contract is signed.
- Which of the following is a key benefit of a centralized procurement department?
- Increased responsiveness to individual project needs.
- Greater flexibility in negotiating contract terms.
- Standardization of procurement processes and documents.
- Enhanced understanding of specific project requirements.
- A project team is outsourcing a portion of the project work for the first time. What is the MOST important initial step?
- Sending out requests for proposals to potential sellers.
- Conducting a thorough make-or-buy analysis.
- Developing the procurement management plan.
- Defining the project requirements in detail.
- What is the purpose of a Request for Quotation (RFQ)?
- To solicit technical proposals from potential sellers.
- To obtain pricing information for well-defined products or services.
- To invite sellers to participate in a bidding process.
- To negotiate the terms and conditions of a contract.
- Which contract type carries the MOST risk for the buyer?
- Firm-Fixed-Price (FFP)
- Cost-Plus-Award-Fee (CPAF)
- Time and Materials (T&M)
- Fixed-Price Incentive Fee (FPIF)
- What is a key objective of the Close Procurements process?
- To ensure all deliverables have been accepted.
- To formally acknowledge the completion of the contractual relationship.
- To identify potential sellers for future projects.
- Both A and B.
- During proposal evaluation, which technique involves assigning numerical scores to different aspects of each proposal based on predefined criteria?
- Screening system
- Weighting system
- Independent estimates
- Negotiation
- Which of the following is a common output of the Plan Stakeholder Engagement process that can significantly influence the procurement strategy?
- Stakeholder register
- Stakeholder engagement plan
- Communications management plan
- Risk management plan
- What is the purpose of a performance bond in a contract?
- To guarantee the seller will complete the work as specified.
- To protect the buyer against the seller’s financial instability.
- To ensure the seller pays its subcontractors on time.
- To provide a financial incentive for early completion.
- In a Time and Materials (T&M) contract, what is the buyer’s primary risk?
- Unexpected increases in material costs.
- The final cost of the project may be higher than anticipated.
- The seller may not have the necessary expertise.
- Delays in project completion due to seller inefficiency.
- What is the BEST approach for handling changes to a contract?
- Implement the changes immediately to keep the project on schedule.
- Only accept changes that are absolutely necessary.
- Follow a formal change control process outlined in the contract.
- Negotiate the cost and schedule impact after the change is implemented.
- Which of the following is a key consideration when determining the type of contract to use?
- The buyer’s preference for risk.
- The complexity of the requirements.
- The availability of potential sellers.
- All of the above.
- What is the purpose of bidder conferences (or contractor conferences)?
- To allow sellers to present their proposals to the buyer.
- To ensure all prospective sellers have a clear and common understanding of the procurement requirements.
- To negotiate the final contract terms with the selected seller.
- To evaluate the technical capabilities of potential sellers.
- Which document describes how the procurement processes will be planned, executed, and controlled?
- Project Management Plan
- Procurement Management Plan
- Contract
- Statement of Work (SOW)
- What is the term for a situation where a seller fails to meet the obligations specified in the contract?
- Breach of contract
- Force majeure
- Indemnification
- Warranty
- Which of the following is a characteristic of a well-defined Statement of Work (SOW)?
- It is flexible and allows for changes as the project progresses.
- It clearly and concisely describes the work to be done, deliverables, and timelines.
- It focuses primarily on the high-level objectives of the procurement.
- It includes pricing details and payment terms.
- What is the purpose of a make-or-buy analysis?
- To determine whether a particular work package should be outsourced or performed by the project team.
- To evaluate the capabilities of potential sellers.
- To develop the criteria for selecting a seller.
- To estimate the cost of the procured items or services.
- Which contract type is often used when the exact scope of work is not clearly defined at the outset?
- Firm-Fixed-Price (FFP)
- Cost-Plus-Fixed-Fee (CPFF)
- Fixed-Price Incentive Fee (FPIF)
- Purchase Order
- What is the significance of “privity of contract”?
- It refers to the legal relationship between the parties who entered into the contract.
- It ensures that all subcontractors are bound by the terms of the main contract.
- It allows third parties to enforce the terms of a contract.
- It defines the ethical obligations of the contracting parties.
- During the Control Procurements process, what is used to formally accept and document that the seller has met the contract requirements?
- Inspection reports
- Performance reports
- Payment approvals
- Contract closure documentation
- Which of the following is a potential disadvantage of outsourcing project work?
- Increased control over the project schedule.
- Reduced need for specialized skills within the project team.
- Loss of control over the outsourced work.
- Lower overall project costs.
- What is the purpose of a Request for Proposal (RFP)?
- To obtain pricing for standard off-the-shelf items.
- To solicit detailed technical and cost proposals from potential sellers.
- To invite sellers to negotiate contract terms.
- To gather information about potential sellers’ qualifications.
- In a Cost-Plus-Award-Fee (CPAF) contract, the award fee is typically based on what?
- The seller’s ability to complete the work under budget.
- The buyer’s subjective evaluation of the seller’s performance.
- The seller’s adherence to the project schedule.
- The seller’s overall profitability on the contract.
- What is the BEST way to handle a conflict with a seller during contract execution?
- Immediately escalate the issue to senior management.
- Refer to the dispute resolution process outlined in the contract.
- Publicly criticize the seller’s performance to exert pressure.
- Unilaterally change the contract terms to resolve the issue.
- Which of the following is a key input to the Plan Procurement Management process?
- Project budget
- Project schedule
- Risk register
- All of the above
- What is the purpose of source selection criteria?
- To define the work that needs to be procured.
- To evaluate seller proposals and select the most qualified seller.
- To establish the terms and conditions of the contract.
- To track the performance of the selected seller.
- Which contract type provides the LEAST incentive for the seller to control costs?
- Firm-Fixed-Price (FFP)
- Cost-Plus-Fixed-Fee (CPFF)
- Fixed-Price Incentive Fee (FPIF)
- Time and Materials (T&M)
- What is a common reason for contract termination for convenience?
- The seller has breached the contract terms.
- The buyer no longer needs the goods or services.
- The seller has become insolvent.
- There has been a significant change in government regulations.
- During the Conduct Procurements process, what is the purpose of negotiations?
- To finalize the contract terms and conditions with the selected seller.
- To evaluate the technical capabilities of potential sellers.
- To clarify the buyer’s requirements for all potential sellers.
- To present the buyer’s preferred solution to the sellers.
- Which of the following is a tool or technique used in the Close Procurements process?
- Performance reviews
- Inspections
- Procurement audits
- Payment systems
- What is the potential impact of poorly defined procurement requirements?
- Increased competition among potential sellers.
- Difficulty in evaluating seller proposals objectively.
- Reduced risk of scope creep.
- Lower overall procurement costs.
- Which document formally establishes the buyer-seller relationship and outlines the obligations of each party?
- Statement of Work (SOW)
- Procurement Management Plan
- Contract
- Request for Proposal (RFP)
- In a Fixed-Price Incentive Fee (FPIF) contract, what happens if the seller exceeds the target cost?
- The seller receives the target fee regardless of the actual cost.
- The buyer and seller share the cost overrun according to the sharing ratio.
- The seller is penalized and receives a reduced fee.
- The contract is renegotiated.
- What is the significance of force majeure in a contract?
- It defines the payment terms and schedule.
- It specifies the warranties provided by the seller.
- It outlines unforeseen events that may excuse a party from fulfilling its obligations.
- It establishes the intellectual property rights related to the procured items.
- Which of the following is a key benefit of using standard contract templates?
- They can be easily customized for any type of procurement.
- They help ensure consistency and reduce the risk of legal issues.
- They eliminate the need for legal review.
- They always offer the most favorable terms for the buyer.
- During the Monitor and Control Project Work process, what information might trigger a change request related to a procurement?
- A delay in a seller’s delivery schedule.
- A positive performance report from a seller.
- The successful completion of a contract milestone.
- The receipt of an invoice from a seller.
- What is the BEST approach to managing multiple sellers on a large project?
- Treat each seller independently and avoid communication between them.
- Establish clear communication channels and coordination mechanisms.
- Rely on the sellers to manage their own interfaces.
- Only communicate with the primary seller and expect them to manage subcontractors.
- Which of the following is NOT a typical element of a Procurement Management Plan?
- Types of contracts to be used.
- Seller selection criteria.
- Risk management strategies for procurements.
- Detailed technical specifications of the procured items.
- What is the purpose of a letter of intent (LOI) in procurement?
- To formally award a contract to a seller.
- To express the buyer’s preliminary commitment to a seller before a formal contract is signed.
- To document the detailed requirements of the procurement.
- To provide feedback to unsuccessful bidders.
- In which project management process group is the “Conduct Procurements” process located?
- Initiating
- Planning
- Executing
- Monitoring and Controlling
- What is the term for a clause in a contract that limits one party’s liability to the other?
- Indemnification clause
- Warranty clause
- Limitation of liability clause
- Termination clause
Answers
- To identify lessons learned in the procurement process.
- Cost-Plus-Fixed-Fee (CPFF)
- Statement of Work (SOW)
- Independent cost estimates
- Review the contract terms and conditions regarding delays and potential remedies.
- Closed procurements
- An agreement where one party makes an offer that can only be accepted by the other party’s performance.
- To emphasize the importance of certain criteria over others.
- $112,000
- Early in the Plan Procurement Management process.
- Standardization of procurement processes and documents.
- Conducting a thorough make-or-buy analysis.
- To obtain pricing information for well-defined products or services.
- Time and Materials (T&M)
- Both A and B.
- Weighting system
- Stakeholder engagement plan
- To guarantee the seller will complete the work as specified.
- The final cost of the project may be higher than anticipated.
- Follow a formal change control process outlined in the contract.
- All of the above.
- To ensure all prospective sellers have a clear and common understanding of the procurement requirements.
- Procurement Management Plan
- Breach of contract
- It clearly and concisely describes the work to be done, deliverables, and timelines.
- To determine whether a particular work package should be outsourced or performed by the project team.
- Cost-Plus-Fixed-Fee (CPFF)
- It refers to the legal relationship between the parties who entered into the contract.
- Contract closure documentation
- Loss of control over the outsourced work.
- To solicit detailed technical and cost proposals from potential sellers.
- The buyer’s subjective evaluation of the seller’s performance.
- Refer to the dispute resolution process outlined in the contract.
- All of the above
- To evaluate seller proposals and select the most qualified seller.
- Cost-Plus-Fixed-Fee (CPFF)
- The buyer no longer needs the goods or services.
- To finalize the contract terms and conditions with the selected seller.
- Procurement audits
- Difficulty in evaluating seller proposals objectively.
- Contract
- The buyer and seller share the cost overrun according to the sharing ratio.
- It outlines unforeseen events that may excuse a party from fulfilling its obligations.
- They help ensure consistency and reduce the risk of legal issues.
- A delay in a seller’s delivery schedule.
- Establish clear communication channels and coordination mechanisms.
- Detailed technical specifications of the procured items.
- To express the buyer’s preliminary commitment to a seller before a formal contract is signed.
- Executing
- Limitation of liability clause