- What is the MOST important factor to consider when developing a cost management plan?
- The project budget.
- Stakeholder requirements.
- The project schedule.
- The project team’s experience.
- Which of the following is a characteristic of parametric estimating?
- It uses historical data from similar projects.
- It involves a detailed, bottom-up approach.
- It uses statistical relationships between variables.
- It considers optimistic, pessimistic, and most likely scenarios.
- What is the term for the authorized budget assigned to scheduled work?
- Actual Cost (AC)
- Earned Value (EV)
- Planned Value (PV)
- Budget at Completion (BAC)
- Which of the following is a primary input to the Control Costs process?
- Project Scope Statement
- Risk Management Plan
- Work Performance Data
- Stakeholder Management Plan
- What is the formula for calculating the Estimate to Complete (ETC) when the initial plan is flawed and the CPI is not expected to improve?
- BAC – EV
- EAC – AC
- BAC / CPI
- EAC / CPI
- Which cost management tool helps to visualize and track the project’s cost performance over time, allowing for the identification of trends and potential future deviations?
- Cost Management Plan
- Earned Value Analysis
- Funding Limit Reconciliation
- Reserve Analysis
- What is the difference between contingency reserves and management reserves?
- Contingency reserves are for known risks, while management reserves are for unknown risks.
- Management reserves are part of the performance measurement baseline, while contingency reserves are not.
- Contingency reserves are controlled by the project manager, while management reserves require management approval.
- There is no significant difference between the two; they are interchangeable terms.
- Which of the following is an example of a variable cost?
- Rent for the project office
- Salaries of permanent project team members
- Cost of raw materials used in production
- Insurance premiums for the project
- What is the expected range of accuracy for an analogous estimate?
- -5% to +10%
- -10% to +25%
- -25% to +75%
- -50% to +100%
- Which of the following is a tool and technique used in the Determine Budget process?
- Earned Value Analysis
- Trend Analysis
- Cost Aggregation
- Variance Analysis
- A project has a planned value (PV) of $800, an earned value (EV) of $700, and an actual cost (AC) of $750. What is the Schedule Variance (SV)?
- $50
- -$50
- $100
- -$100
- Which of the following is a potential output of the Estimate Costs process?
- Project Budget
- Cost Management Plan
- Basis of Estimates
- Performance Reports
- What is the primary goal of the Plan Cost Management process?
- To create the project budget.
- To define how costs will be managed throughout the project.
- To monitor and control project spending.
- To estimate the resources needed for the project.
- Which of the following is NOT a typical element of the project budget?
- Direct Costs
- Indirect Costs
- Contingency Reserves
- Opportunity Costs
- What is the purpose of a Basis of Estimates?
- To document how the project budget was developed.
- To explain the assumptions and constraints used in cost estimates.
- To track the actual costs incurred during the project.
- To forecast the final project cost.
- Which cost estimating technique is generally the most accurate?
- Analogous estimating
- Parametric estimating
- Bottom-up estimating
- Three-point estimating
- What does a Cost Performance Index (CPI) greater than 1 indicate?
- The project is over budget.
- The project is under budget.
- The project is behind schedule.
- The project is ahead of schedule.
- Which of the following is a benefit of using Earned Value Management (EVM)?
- Improved team communication.
- Enhanced stakeholder engagement.
- Early identification of cost and schedule variances.
- More accurate risk assessments.
- What is the total approved budget established for the project called?
- Cost Baseline
- Project Budget
- Budget at Completion (BAC)
- Performance Measurement Baseline
- Which of the following is a tool used for forecasting in the Control Costs process?
- Variance Analysis
- Trend Analysis
- Earned Value Analysis
- Reserve Analysis
- A project manager is reviewing a cost report that shows a significant negative Cost Variance (CV). What should be the NEXT step?
- Immediately cut project spending.
- Re-baseline the project budget.
- Investigate the reasons for the variance.
- Report the variance to the stakeholders.
- Which of the following is a key input to the Determine Budget process?
- Project Charter
- Staffing Management Plan
- Cost Estimates
- Communications Management Plan
- What is the formula for calculating the three-point estimate using the triangular distribution?
- (Optimistic + Pessimistic + Most Likely) / 2
- (Optimistic + 4 * Most Likely + Pessimistic) / 6
- (Optimistic + Most Likely + Pessimistic) / 3
- (Optimistic + 2 * Most Likely + Pessimistic) / 4
- Which of the following is a characteristic of fixed costs?
- They change in proportion to the level of production.
- They remain constant regardless of the level of production.
- They are directly attributable to specific project activities.
- They are incurred only when the project is behind schedule.
- What is the purpose of funding limit reconciliation?
- To allocate budget to different work packages.
- To ensure that expenditures align with funding availability.
- To track the actual spending against the planned budget.
- To forecast the final cost of the project.
- Which of the following is a tool and technique used in the Plan Cost Management process?
- Earned Value Analysis
- Reserve Analysis
- Expert Judgment
- Cost Aggregation
- What does a Schedule Performance Index (SPI) less than 1 indicate?
- The project is ahead of schedule.
- The project is behind schedule.
- The project is on budget.
- The project is over budget.
- Which of the following is a primary responsibility of the project manager in project cost management?
- Approving all project expenditures.
- Developing the detailed cost estimates.
- Ensuring the project is completed within the approved budget.
- Negotiating contracts with vendors.
- What is the process of establishing the total budget for the project, including contingency reserves?
- Estimate Costs
- Plan Cost Management
- Determine Budget
- Control Costs
- Which of the following is a potential consequence of poor project cost management?
- Increased team satisfaction.
- Improved product quality.
- Project failure due to budget overruns.
- Enhanced communication with stakeholders.
- A project manager is using historical data adjusted for inflation and current market conditions to estimate costs. Which estimating technique is being used?
- Analogous estimating
- Parametric estimating
- Bottom-up estimating
- Three-point estimating
- What is the formula for calculating the To-Complete Performance Index (TCPI) based on the Estimate at Completion (EAC)?
- (BAC – EV) / (EAC – AC)
- (EAC – AC) / (BAC – EV)
- EAC / EV
- EAC / AC
- Which of the following is a key output of the Control Costs process?
- Cost Management Plan Updates
- Project Schedule Updates
- Performance Reports
- Risk Register Updates
- What is the purpose of trend analysis in project cost management?
- To compare planned costs with actual costs at a specific point in time.
- To forecast future cost performance based on past trends.
- To determine the root causes of cost variances.
- To allocate contingency reserves to project activities.
- Which of the following is NOT a typical input to the Estimate Costs process?
- Scope Baseline
- Project Schedule
- Resource Calendars
- Stakeholder Register
- What is the expected range of accuracy for a bottom-up estimate?
- -5% to +10%
- -10% to +25%
- -25% to +75%
- -50% to +100%
- Which of the following is an example of a semi-variable cost?
- Monthly internet service with a fixed base fee and usage charges.
- Annual insurance premium.
- Salary of a project manager.
- Cost of raw materials.
- What is the significance of the performance measurement baseline in cost management?
- It is the original approved budget against which project performance is measured.
- It includes management reserves for unforeseen work.
- It is updated regularly to reflect approved scope changes.
- It is a high-level estimate used for initial project approval.
- Which of the following is a tool and technique used in the Determine Budget process?
- Reserve Analysis
- Earned Value Analysis
- Variance Analysis
- Trend Analysis
- A project has a Budget at Completion (BAC) of $2,000,000. The Earned Value (EV) is $1,200,000 and the Actual Cost (AC) is $1,500,000. What is the Cost Performance Index (CPI)?
- 0.8
- 1.25
- 0.6
- 1.67
- Which of the following is a key input to the Plan Cost Management process?
- Project Charter
- Project Management Plan
- Stakeholder Register
- Risk Register
- What is the formula for calculating the Estimate at Completion (EAC) when future performance is expected to improve?
- AC + ETC
- BAC / CPI
- AC + (BAC – EV) / CPI
- BAC – CV
- Which of the following is a potential cause of scope creep and its impact on project costs?
- Clearly defined project requirements.
- Effective change control processes.
- Unapproved changes to the project scope.
- Realistic project timelines.
- What is the purpose of the Cost Management Plan?
- To define the project’s objectives and deliverables.
- To outline the processes for planning, managing, and controlling project costs.
- To document the project’s schedule and resource requirements.
- To describe how stakeholders will be engaged throughout the project.
- Which of the following is a tool used for data representation in the Control Costs process?
- Cost Aggregation
- Reserve Analysis
- S-curves
- Funding Limit Reconciliation
- What is the expected range of accuracy for a three-point estimate?
- It depends on the weighting of the optimistic, pessimistic, and most likely estimates.
- -5% to +10%
- -25% to +75%
- -50% to +100%
- Which of the following is NOT a typical type of reserve used in project cost management?
- Contingency Reserve
- Management Reserve
- Schedule Reserve
- Budget Reserve
- What is the significance of the Budget at Completion (BAC)?
- It is the actual cost incurred on the project to date.
- It is the total planned value of the work completed to date.
- It is the total planned value of the work.
- It is the estimated cost to complete the remaining work.
- Which of the following is a tool and technique used in the Estimate Costs process?
- Cost Aggregation
- Funding Limit Reconciliation
- Reserve Analysis
- Vendor Bid Analysis
- A project has a Budget at Completion (BAC) of $750,000. The Estimate at Completion (EAC) is $825,000. What is the Variance at Completion (VAC)?
- $75,000
- -$75,000
- $1,575,000
- -$750,000
Answers
- Stakeholder requirements.
- It uses statistical relationships between variables.
- Planned Value (PV)
- Work Performance Data
- BAC / CPI
- Earned Value Analysis
- Contingency reserves are for known risks, while management reserves are for unknown risks.
- Cost of raw materials used in production
- -25% to +75%
- Cost Aggregation
- -$100
- Basis of Estimates
- To define how costs will be managed throughout the project.
- Opportunity Costs
- To explain the assumptions and constraints used in cost estimates.
- Bottom-up estimating
- The project is under budget.
- Early identification of cost and schedule variances.
- Budget at Completion (BAC)
- Trend Analysis
- Investigate the reasons for the variance.
- Cost Estimates
- (Optimistic + Most Likely + Pessimistic) / 3
- They remain constant regardless of the level of production.
- To ensure that expenditures align with funding availability.
- Expert Judgment
- The project is behind schedule.
- Ensuring the project is completed within the approved budget.
- Determine Budget
- Project failure due to budget overruns.
- Analogous estimating
- (BAC – EV) / (EAC – AC)
- Performance Reports
- To forecast future cost performance based on past trends.
- Stakeholder Register
- -5% to +10%
- Monthly internet service with a fixed base fee and usage charges.
- It is the original approved budget against which project performance is measured.
- Reserve Analysis
- 0.8
- Project Charter
- AC + (BAC – EV) / CPI
- Unapproved changes to the project scope.
- To outline the processes for planning, managing, and controlling project costs.
- S-curves
- It depends on the weighting of the optimistic, pessimistic, and most likely estimates.
- Schedule Reserve
- It is the total planned value of the work.
- Vendor Bid Analysis
- -$75,000