Project Cost Management Quiz

Please enter your email:

1. A project has a Budget at Completion (BAC) of $500,000. The Cost Performance Index (CPI) is 0.9 and the Schedule Performance Index (SPI) is 1.1. If the team continues to perform at the same cost efficiency, what is the Estimate at Completion (EAC)?

 
 
 
 

2. Which of the following is a key input to the Plan Cost Management process?

 
 
 
 

3. What is the purpose of a cost management plan?

 
 
 
 

4. What is the formula for calculating the To-Complete Performance Index (TCPI) based on the Estimate at Completion (EAC)?

 
 
 
 

5. Which of the following is a key input to the Control Costs process?

 
 
 
 

6. What is the formula for calculating the Schedule Performance Index (SPI)?

 
 
 
 

7. What is the formula for calculating the Estimate to Complete (ETC) when the cost variance is considered atypical and future performance is expected to be similar to past performance?

 
 
 
 

8. What is the formula for calculating the Estimate to Complete (ETC) when the initial plan is flawed and the CPI is not expected to improve?

 
 
 
 

9. What is the purpose of reserve analysis in cost management?

 
 
 
 

10. Which of the following is a tool and technique used in the Determine Budget process?

 
 
 
 

11. What is the formula for calculating the Estimate at Completion (EAC) when future performance is expected to improve?

 
 
 
 

12. Which of the following is a potential output of the Estimate Costs process?

 
 
 
 

13. Which of the following is NOT a typical element of the project budget?

 
 
 
 

14. Which of the following is a key output of the Control Costs process?

 
 
 
 

15. What is the purpose of a Basis of Estimates?

 
 
 
 

16. Which of the following is a key output of the Estimate Costs process?

 
 
 
 

17. A project manager is reviewing the budget for a critical path activity and notices that the actual cost incurred is significantly higher than the planned value. What is the MOST likely immediate concern for the project manager?

 
 
 
 

18. What is the term for the authorized budget assigned to scheduled work?

 
 
 
 

19. What does a Schedule Performance Index (SPI) less than 1 indicate?

 
 
 
 

20. Which of the following is a tool and technique used in the Plan Cost Management process?

 
 
 
 

21. Which of the following is a benefit of using Earned Value Management (EVM)?

 
 
 
 

22. What does a Cost Performance Index (CPI) of 0.8 indicate?

 
 
 
 

23. What is the MOST important factor to consider when developing a cost management plan?

 
 
 
 

24. Which of the following is a primary responsibility of the project manager in project cost management?

 
 
 
 

25. Which of the following is a potential consequence of poor project cost management?

 
 
 
 

26. What is the total approved budget established for the project called?

 
 
 
 

27. What does a Cost Performance Index (CPI) greater than 1 indicate?

 
 
 
 

28. Which of the following is a key input to the Determine Budget process?

 
 
 
 

29. Which of the following is an example of a direct cost?

 
 
 
 

30. A project manager is using a statistical relationship between historical data and project variables to estimate costs. Which estimating technique is being used?

 
 
 
 

31. What is the expected range of accuracy for a bottom-up estimate?

 
 
 
 

32. What is the significance of the performance measurement baseline in cost management?

 
 
 
 

33. During a project execution, a stakeholder requests a significant scope change. What should the project manager do FIRST with regard to cost management?

 
 
 
 

34. Which of the following is a tool and technique used in the Control Costs process?

 
 
 
 

35. Which of the following is an example of an indirect cost?

 
 
 
 

36. What is the total planned value of the work scheduled to be completed by a specific date called?

 
 
 
 

37. What is the process of aggregating the estimated costs of individual work packages or activities to establish an overall cost baseline?

 
 
 
 

38. What is the formula for calculating the Estimate at Completion (EAC) when the current variances are seen as typical and future performance is expected to be similar?

 
 
 
 

39. Which of the following is a tool and technique used in the Estimate Costs process?

 
 
 
 

40. A project manager is using historical data adjusted for inflation and current market conditions to estimate costs. Which estimating technique is being used?

 
 
 
 

41. What is the formula for calculating the three-point estimate using the triangular distribution?

 
 
 
 

42. Which cost estimating technique is generally the most accurate?

 
 
 
 

43. Which of the following is a characteristic of sunk costs?

 
 
 
 

44. A project has a Budget at Completion (BAC) of $750,000. The Estimate at Completion (EAC) is $825,000. What is the Variance at Completion (VAC)?

 
 
 
 

45. What is the formula for calculating the To-Complete Performance Index (TCPI) based on the Budget at Completion (BAC)?

 
 
 
 

46. A project manager is reviewing the performance reports and notices a consistent negative cost variance. What does this indicate?

 
 
 
 

47. Which of the following is an example of a variable cost?

 
 
 
 

48. What is the expected range of accuracy for an analogous estimate?

 
 
 
 

49. Which of the following is an example of a semi-variable cost?

 
 
 
 

50. What is the expected range of accuracy for a budgetary estimate?

 
 
 
 

51. What is the purpose of the To-Complete Performance Index (TCPI)?

 
 
 
 

52. Which of the following is a potential cause of scope creep and its impact on project costs?

 
 
 
 

53. What is the primary goal of the Plan Cost Management process?

 
 
 
 

54. What is the significance of the Budget at Completion (BAC)?

 
 
 
 

55. Which of the following is NOT a type of cost typically included in a project budget?

 
 
 
 

56. Which of the following is a tool used for forecasting in the Control Costs process?

 
 
 
 

57. Which of the following is a tool used for data representation in the Control Costs process?

 
 
 
 

58. What is the process of establishing the total budget for the project, including contingency reserves?

 
 
 
 

59. A project has a Budget at Completion (BAC) of $1,000,000. After 50% of the planned work is completed, the Earned Value (EV) is $450,000 and the Actual Cost (AC) is $550,000. What is the Cost Variance (CV)?

 
 
 
 

60. What is the purpose of funding limit reconciliation?

 
 
 
 

61. Which cost management technique involves comparing actual project performance to planned performance and taking corrective action when necessary?

 
 
 
 

62. What is the purpose of trend analysis in project cost management?

 
 
 
 

63. Which cost management tool helps to visualize and track the project’s cost performance over time, allowing for the identification of trends and potential future deviations?

 
 
 
 

64. Which of the following is a tool used for data analysis in the Control Costs process?

 
 
 
 

65. Which of the following is NOT a typical input to the Estimate Costs process?

 
 
 
 

66. What does a Schedule Performance Index (SPI) of 1.1 indicate?

 
 
 
 

67. Which of the following is a primary goal of project cost management?

 
 
 
 

68. Which of the following is a potential cause of cost overruns on a project?

 
 
 
 

69. Which cost estimating technique involves estimating the cost of individual work packages and then summing them to get a total project cost?

 
 
 
 

70. A project has a Budget at Completion (BAC) of $2,000,000. The Earned Value (EV) is $1,200,000 and the Actual Cost (AC) is $1,500,000. What is the Cost Performance Index (CPI)?

 
 
 
 

71. Which of the following formulas is used to calculate the Cost Performance Index (CPI)?

 
 
 
 

72. A project has a planned value (PV) of $800, an earned value (EV) of $700, and an actual cost (AC) of $750. What is the Schedule Variance (SV)?

 
 
 
 

73. What is the expected range of accuracy for a three-point estimate?

 
 
 
 

74. A project manager is asked to provide a cost estimate quickly based on historical data from similar projects. Which estimating technique is MOST likely being used?

 
 
 
 

75. What is the purpose of variance analysis in project cost management?

 
 
 
 

76. What is the expected range of accuracy for a definitive estimate?

 
 
 
 

77. Which of the following tools and techniques is used in the Plan Cost Management process?

 
 
 
 

78. Which of the following is NOT a characteristic of a well-defined cost baseline?

 
 
 
 

79. Which of the following is a tool and technique used in the Determine Budget process?

 
 
 
 

80. Which of the following is a tool and technique used in the Estimate Costs process?

 
 
 
 

81. Which of the following is NOT a typical element of a cost management plan?

 
 
 
 

82. What is a contingency reserve typically used for in project cost management?

 
 
 
 

83. What is the purpose of funding limit reconciliation?

 
 
 
 

84. Which of the following is a key input to the Estimate Costs process?

 
 
 
 

85. What is the difference between a rough order of magnitude (ROM) estimate and a definitive estimate?

 
 
 
 

86. What is the purpose of management reserves in project cost management?

 
 
 
 

87. What is the difference between contingency reserves and management reserves?

 
 
 
 

88. Which of the following is NOT a typical input to the Determine Budget process?

 
 
 
 

89. Which of the following is a primary input to the Control Costs process?

 
 
 
 

90. A project has a planned value (PV) of $500, an earned value (EV) of $450, and an actual cost (AC) of $550. What is the cost variance (CV) for this project?

 
 
 
 

91. Which of the following is a characteristic of fixed costs?

 
 
 
 

92. Which of the following is NOT a typical type of reserve used in project cost management?

 
 
 
 

93. What is the formula for calculating the variance at completion (VAC)?

 
 
 
 

94. Which of the following is a characteristic of parametric estimating?

 
 
 
 

95. Which of the following is a key output of the Determine Budget process?

 
 
 
 

96. A project manager is reviewing a cost report that shows a significant negative Cost Variance (CV). What should be the NEXT step?

 
 
 
 

97. Which of the following is a key benefit of effective project cost management?

 
 
 
 

98. What is the primary purpose of the Control Costs process?

 
 
 
 

99. What is the purpose of the Cost Management Plan?

 
 
 
 

100. Which of the following is a potential output of the Control Costs process?

 
 
 
 

Question 1 of 100