Project Risk Management Quiz

Please enter your email:

1. What is the purpose of the Monitor Risks process?

 
 
 
 

2. Which of the following is a common input to the Perform Qualitative Risk Analysis process?

 
 
 
 

3. A risk trigger is BEST described as:

 
 
 
 

4. What is the primary goal of risk management planning?

 
 
 
 

5. A project manager is reviewing the risk register and notices a risk with a high impact but a very low probability. What is the MOST appropriate course of action?

 
 
 
 

6. Which of the following is a risk response strategy that involves allocating some or all of the ownership of an opportunity to a third party who is best able to realize it for the benefit of the project?

 
 
 
 

7. Which of the following BEST describes residual risks?

 
 
 
 

8. A project team has identified a risk that could result in a significant delay to the project schedule. They decide to add buffer time to the schedule to mitigate this potential impact. Which risk response strategy are they using?

 
 
 
 

9. A project manager is monitoring the risk register and notices that the probability of a specific risk has increased significantly. What should the project manager do NEXT?

 
 
 
 

10. A project manager is reviewing potential risks and wants to visually represent the hierarchy of identified risks. Which of the following tools would be MOST suitable for this purpose?

 
 
 
 

11. Which of the following techniques uses expected monetary value (EMV) to analyze potential outcomes of different project scenarios?

 
 
 
 

12. A project manager is using checklists for risk identification. What is a key advantage of using this technique?

 
 
 
 

13. During the risk assessment process, a risk is determined to have a high probability of occurrence and a high impact on project objectives. According to a typical probability and impact matrix, how should this risk be categorized?

 
 
 
 

14. A project team has identified a risk with a low probability and a high impact. Which of the following is the MOST appropriate initial action?

 
 
 
 

15. Which of the following is an example of a positive risk (opportunity) that could be identified in a project?

 
 
 
 

16. What is the primary purpose of a risk audit?

 
 
 
 

17. A project manager is facilitating a risk identification meeting with the project team and key stakeholders. Which of the following techniques is MOST effective for generating a comprehensive list of potential risks?

 
 
 
 

18. Which of the following is a primary goal of the Plan Risk Management process?

 
 
 
 

19. Which of the following is a key input to the Perform Qualitative Risk Analysis process?

 
 
 
 

20. Which of the following is a key element of the risk management plan?

 
 
 
 

21. During a project execution, a previously unidentified risk emerges. What is the FIRST thing the project manager should do?

 
 
 
 

22. Which of the following BEST describes the purpose of identifying risks in a project?

 
 
 
 

23. A project manager is using an influence diagram. What is the primary purpose of this tool in risk management?

 
 
 
 

24. Which of the following BEST describes a fallback plan?

 
 
 
 

25. Which of the following BEST describes secondary risks?

 
 
 
 

26. Which of the following BEST describes a management reserve?

 
 
 
 

27. Which of the following is a risk response strategy that involves unilaterally taking action to eliminate the threat?

 
 
 
 

28. Which of the following is a characteristic of a well-defined risk statement?

 
 
 
 

29. Which of the following is a tool used in Perform Qualitative Risk Analysis?

 
 
 
 

30. Which of the following is a quantitative risk analysis technique that helps to determine the impact of variations in input variables on a dependent variable?

 
 
 
 

31. During a project meeting, a stakeholder raises a new potential risk. What should the project manager do FIRST?

 
 
 
 

32. A project manager is reviewing the risk register and notices that a risk event has occurred. What should be the project manager’s NEXT step?

 
 
 
 

33. Which of the following is NOT a typical element of a risk management plan?

 
 
 
 

34. Which of the following stakeholders is typically responsible for approving the risk management plan?

 
 
 
 

35. Which of the following is NOT a typical output of the Monitor Risks process?

 
 
 
 

36. A project manager is reviewing the project budget and notices a significant amount allocated as management reserve. What is the purpose of the management reserve?

 
 
 
 

37. What is the primary purpose of performing assumption analysis?

 
 
 
 

38. Which of the following is NOT a typical tool or technique for identifying risks?

 
 
 
 

39. Which of the following is a tool and technique used in the Monitor Risks process?

 
 
 
 

40. A project team has identified several potential risks and is now determining the likelihood of these risks occurring and their potential impact on the project. Which process are they currently performing?

 
 
 
 

41. What is the purpose of a risk owner?

 
 
 
 

42. Which of the following stakeholders is typically MOST involved in the risk management process?

 
 
 
 

43. A project team is using simulation to model the potential impact of schedule uncertainties on the project completion date. Which quantitative risk analysis technique are they using?

 
 
 
 

44. Which of the following is a common cause of opportunities in a project?

 
 
 
 

45. During project execution, a new risk is identified. What process should the project manager follow to address this risk?

 
 
 
 

46. Which of the following risk response strategies involves taking action to reduce the probability of occurrence or impact of a risk?

 
 
 
 

47. Which of the following is NOT a typical element of the risk register?

 
 
 
 

48. A project manager is concerned about the impact of a delay in a critical deliverable. Which risk analysis technique would be MOST helpful in determining the potential impact of this delay on the overall project schedule?

 
 
 
 

49. Which of the following is a tool used in the Identify Risks process?

 
 
 
 

50. Which of the following is a key input to the Monitor Risks process?

 
 
 
 

51. Which of the following BEST describes a contingency reserve?

 
 
 
 

52. Which of the following is NOT a typical element of a risk report?

 
 
 
 

53. A project manager is using a probability and impact matrix with scales of Very Low, Low, Medium, High, and Very High. A risk with a “High” probability and a “Medium” impact would likely be categorized as:

 
 
 
 

54. Which of the following is a key input to the Plan Risk Management process?

 
 
 
 

55. A project team is brainstorming potential risks. Which of the following is a key principle for effective brainstorming?

 
 
 
 

56. A project manager is reviewing the project schedule and identifies a critical path activity with a high degree of uncertainty in its duration. Which risk analysis technique would be MOST appropriate to assess the potential impact of this uncertainty on the overall project completion date?

 
 
 
 

57. Which of the following is a key benefit of using a risk breakdown structure (RBS)?

 
 
 
 

58. Which of the following risk response strategies aims to increase the probability and/or positive impact of an opportunity?

 
 
 
 

59. A project team decides to purchase insurance to cover potential financial losses due to a specific risk. Which risk response strategy are they employing?

 
 
 
 

60. Which of the following is a quantitative risk analysis technique that models a range of potential outcomes by performing multiple simulations?

 
 
 
 

61. A project team is considering two different suppliers for a critical component. Supplier A has a lower cost but a higher risk of late delivery, while Supplier B has a higher cost but a lower risk of late delivery. Which risk analysis technique could help the team decide which supplier to choose based on cost and schedule risks?

 
 
 
 

62. A project team has identified a risk that, if it occurs, will have a significant negative impact on the project schedule but a minimal impact on the budget. Which risk response strategy might be MOST appropriate?

 
 
 
 

63. Which of the following is a primary output of the Perform Quantitative Risk Analysis process that represents the likelihood of achieving specific project objectives?

 
 
 
 

64. Which of the following risk response strategies is appropriate for risks with a low probability and low impact?

 
 
 
 

65. A project manager is reviewing the lessons learned from previous projects. How can this information be MOST helpful for the current project’s risk management?

 
 
 
 

66. What is the purpose of establishing risk thresholds?

 
 
 
 

67. Which of the following is a risk response strategy that involves changing the project objectives to avoid the risk?

 
 
 
 

68. Which of the following outputs of the Identify Risks process provides a structured list of identified risks along with their descriptions?

 
 
 
 

69. What is the primary purpose of a risk report?

 
 
 
 

70. Which of the following risk response strategies involves changing the project plan to eliminate the risk or protect the project objectives from its impact?

 
 
 
 

71. Which of the following is a key characteristic of effective risk management?

 
 
 
 

72. Which of the following is a key benefit of performing risk management throughout the project lifecycle?

 
 
 
 

73. Which of the following is NOT a common category of project risks?

 
 
 
 

74. Which of the following is a benefit of using standardized risk categories in a project?

 
 
 
 

75. Which of the following is a characteristic of effective risk monitoring and control?

 
 
 
 

76. A project manager is reviewing potential risks and wants to understand which risks have the most potential impact on the project. Which of the following tools would be MOST helpful?

 
 
 
 

77. During project closure, what should be done with the risk register?

 
 
 
 

78. During project closure, what should be done with the lessons learned related to risk management?

 
 
 
 

79. What is the relationship between the risk register and the risk management plan?

 
 
 
 

80. Which of the following is a common cause of project risks?

 
 
 
 

81. Which of the following is a key benefit of performing qualitative risk analysis?

 
 
 
 

82. A project manager is facilitating a meeting to review the status of identified risks and the effectiveness of implemented risk responses. Which process is being performed?

 
 
 
 

83. A project manager is facilitating a lessons learned session at the end of a project. What information related to risk management should be captured?

 
 
 
 

84. Which of the following risk response strategies is most suitable for opportunities with a high probability and high positive impact?

 
 
 
 

85. Which of the following is a tool that can be used to visually display the probability and impact of risks?

 
 
 
 

86. Which of the following risk response strategies involves sharing the burden of the risk with a third party?

 
 
 
 

87. Which of the following is a key output of the Perform Quantitative Risk Analysis process?

 
 
 
 

88. A project team is using a probability and impact matrix. A risk with a probability of 0.8 and an impact score of 0.7 would typically fall into which category if the threshold for high risk is 0.56 (probability * impact)?

 
 
 
 

89. A project has a 60% chance of a $100,000 profit and a 40% chance of a $50,000 loss. What is the expected monetary value (EMV) of this project?

 
 
 
 

90. Which of the following is a tool used in the Perform Quantitative Risk Analysis process?

 
 
 
 

91. The process of developing options and actions to enhance opportunities and reduce threats to the achievement of project objectives is known as:

 
 
 
 

92. Which of the following is a key output of the Identify Risks process that contains potential responses to identified risks?

 
 
 
 

93. Which of the following is an example of a risk trigger?

 
 
 
 

94. A project manager is using a decision tree to analyze different project paths based on potential risks and their associated outcomes. What is the primary benefit of using this technique?

 
 
 
 

95. Which of the following is NOT a typical output of the Plan Risk Responses process?

 
 
 
 

96. During project execution, a risk occurs that was identified in the risk register, and a contingency plan was developed. What should the project manager do NEXT?

 
 
 
 

97. Which of the following risk response strategies is appropriate for opportunities with a low probability and low positive impact?

 
 
 
 

98. The level of risk that the organization is willing to accept is known as:

 
 
 
 

99. The risk management plan should include all of the following EXCEPT:

 
 
 
 

100. Which of the following is a tool and technique used in the Plan Risk Responses process?

 
 
 
 

Question 1 of 100